Site Construction Plan & Progress
BALL & SOCKET ARTS DEVELOPMENT PLAN
Phase 1 - 9,000 sf, currently in development
Phase 1 will present a microcosm of the larger Ball & Socket Arts project. It will be a foothold, allowing us to present programming and cultivate donors and partners while we raise funds for Phase 2 and for the more challenging large-scale buildings on-site.
Elements of Phase 1 are:
Full renovation of Building 2 (The Willow Street Building), to house two mission-aligned tenants (the first floor was completed in August 2022)
Full renovation of Building 3 including the first floor Workshop Gallery, the second floor will house a small art gallery, a multi-function room, and offices for Ball & Socket Arts (completed September 2023)
Parking and landscaping along the entire West Main Street frontage (completed)
The creation of a rear parking lot between Building 1 and Building 5, including the spur with direct access to the Farmington Canal Heritage Trail (completed)
Facade rehabilitation of the Front Office Building (underway, with many aspects completed)
New sidewalks and streetscapes along Willow Street (construction beginning autumn 2023 by the Town of Cheshire)
Hazardous materials abatement site-wide (underway)
Phase 2 - 54,000 sf
Phase 2 will be the largest phase, ultimately returning the site to public use. Elements of Phase 2 include:
Remediation systems operational in Building 1
Major structural repairs and fire safety systems installed in Building 1
Beginning of window restoration throughout Building 1
Renovation of 45,000 square feet comprising Building 1 (the main factory building). The final complex will house:
the grand art gallery,
a flexible performance space for music, lectures, readings, film screenings and more
the welcome center,
an interactive historical space,
retail shops (mission-aligned)
a food court, featuring local businesses
a bike shop
Complete renovation of Building 5 (The Power House) to house commercial tenant
Complete parking and landscaping site-wide
Milestones